The Word “Estimate” in a Contract Matters as to a Completion Date
February 12, 2024 —
David Adelstein - Florida Construction Legal UpdatesLanguage in a contract matters. The word “estimates” or “estimated” matters particularly when it comes to a date certain such as a substantial completion or completion date. Remember this.
Here is an example.
In Parque Towers Developers, LLC v. Pilac Management, Ltd., 49 Fla.L.Weekly D190a (Fla. 3d DCA 2024), a trial court held that the developer did not complete the construction of five condominium units by the date in the purchase agreements. The developer appealed because “[t]he agreements contain no date certain for the completion of the units, but rather include a clause that ‘Seller estimates it will substantially complete construction of the Unit, in the manner specified in this Agreement, by December 31, 2017, subject to extensions resulting from ‘Force Majeure (the ‘Outside Date’).’” Parque Towers, supra. Another provision in the purchase agreements stated, “[w]henver this Agreement requires Seller to complete or substantially complete any item of construction, that item will be understood to be complete or substantially complete when so completed or substantially completed in Seller’s opinion. Id.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Bill Proposes First-Ever Federal Workforce Housing Tax Credit for Middle-Class Housing
March 04, 2024 —
Emily K. Bias & Brittany Griffith - Gravel2Gavel Construction & Real Estate Law BlogLegislation was recently introduced to the U.S. Senate and House of Representatives proposing the creation of the first-ever Workforce Housing Tax Credit (WHTC) for middle-income housing developments.
Similar to the existing Low-Income Housing Tax Credit (LIHTC), the WHTC would provide additional federal income tax credits to housing development projects for tenants making between 60% and 100% of Area Median Income (AMI). The allocation of WHTC would be based on a competitive bid process and awarded to developments over a 15-year credit period (as opposed to a 10-year credit period for LIHTC). Developments receiving allocations of WHTC will be subject to affordability requirements during the 15-year credit period and subsequent extended use period of at least 15 years.
Reprinted courtesy of
Emily K. Bias, Pillsbury and
Brittany Griffith, Pillsbury
Ms. Bias may be contacted at emily.bias@pillsburylaw.com
Ms. Griffith may be contacted at brittany.griffith@pillsburylaw.com
Read the full story...
More Clear, But Not Yet Crystal: Virginia Amends its Prompt Payment Law and Legislation Banning “Pay-If-Paid Clauses in Construction Contracts Effective July 1, 2023
November 16, 2023 —
Hanna Lee Blake - ConsensusDocsThe Virginia General Assembly has joined a minority of jurisdictions that ban pay-if-paid clauses in construction contracts on public and private projects. Senate Bill 550 went into effect applying to contracts executed after January 1, 2023, and most recently has been amended effective July 1, 2023. This update highlights the recent amendments to Virginia’s prohibition against pay-if-paid provisions, of which owners and contractors should be aware to ensure that their contracts comply with developing law in the Commonwealth.
Recap on Senate Bill 550
On April 27, 2022, the Virginia General Assembly passed Senate Bill 550, which amended Virginia Code §§ 2.2-4354 and 11-4.6, which govern both public and private sector contracts. In short, SB 550 (as the bill is commonly known) prohibited pay-if-paid clauses, and established fixed deadlines for the payment of invoices on private projects. Previously, Virginia’s Prompt Payment Act only applied to public projects.
Read the full story...Reprinted courtesy of
Hanna Lee Blake, Watt TiederMs. Blake may be contacted at
hblake@watttieder.com
Appellate Court of Maryland Construes Notice Conditions of A312 Performance Bond in Favor of Surety
January 02, 2024 —
Joel P. Williams - White and Williams LLPThe Appellate Court of Maryland issued a reported opinion in a case construing an American Institute of Architects (“AIA”) A312 performance bond. In Wildewood Operating Company, LLC v. WRV Holdings, LLC, et al. 2023 Md. App. LEXIS 720 (Oct. 30, 2023), the Appellate Court of Maryland held that a performance bond surety was discharged from liability where the owner/obligee failed to give the surety notice of the contractor’s default termination until after a third party had completed the work.
The project concerned the construction of an assisted living facility in St. Mary’s County, Maryland. The owner, Wildewood Operating Company, LLC, entered into an A312-2010 performance bond with Clark Turner Construction, LLC, as contractor, and First Indemnity of America Insurance Company, as surety. When Clark Turner failed to complete certain stormwater management work adjacent to the site, Wildewood, Clark Turner, and other parties entered into a Work Agreement to address completion of the work. The surety was not a party to the Work Agreement.
Read the full story...Reprinted courtesy of
Joel P. Williams, White and Williams LLPMr. Williams may be contacted at
williamsj@whiteandwilliams.com
Jury Could Have Found That Scissor Lift Manufacturer Should Have Included “Better” Safety Features
January 02, 2024 —
Garret Murai - California Construction Law BlogA few years ago I listened to an NPR segment called “
What Can Kids Learn by Doing Dangerous Things?” It was about a summer program called the Tinkering School where kids can learn to build things, using tools of course, including power tools.
The founder of the program, Gever Tulley, also wrote a book entitled
50 Dangerous Things (You Should Let Your Children Do), in which he argued that while well-intentioned, children today are overly protected, and that giving children exposure to “slightly” dangerous things can help foster independence, responsibility, and problem-solving as well as a healthy dose of caution.
The plaintiff in the next case might have benefitted from that program.
In
Camacho v. JLG Industries Inc., 93 Cal.App.5th 809 (2023), the Court of Appeals examined whether the manufacturer of a scissor lift should have incorporated “better” safety features when a construction worker fell from the lift.
Read the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
You Say Tomato, I Say Tomahto. But When it Comes to the CalOSHA Appeals Board, They Can Say it Any Way They Please
January 08, 2024 —
Garret Murai - California Construction Law BlogWe lawyers do a fair amount of reading. Documents. Court decisions. Passive aggressive correspondence from opposing counsel. As well as statutes, regulations and administrative guidance. And you might be surprised how often words can be ascribed very different meanings depending on who is reading it. Such, I suppose, is the nature of language. When it comes to public agency interpretations of its own regulations, however, you would be well to heed that authors are often the best interpreters of their own works, or at least that’s how the courts tend to view it, as in the next case L & S Framing Inc. v. California Occupational Safety and Health Appeals Board, Case No. C096386 (July 24, 2023).
The L & S Framing Case
Martin Mariano, an employee of L & S Framing, Inc., suffered a brain injury when he fell from the “second floor” while working on a single family house. What, exactly, this “second floor” was, was a point of a contention in the legal case that followed.
Read the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
CGL Coverage for Liquidated Damages and the Contractual Liability Exclusion
October 09, 2023 —
Stu Richeson - The Dispute ResolverLiquidated delay damages are common in construction contracts and are generally imposed when a contractor fails to achieve substantial completion within the time required by the contract. While contracts like the AIA A201-2017 have provisions for extending the time to achieve substantial completion when delays are caused by circumstances beyond the contractor’s control, delays can result from factors other than improper management or planning and the like, for which the owner is not required to give the contractor additional time. Courts are split on whether there is ever coverage under a CGL policy for contractually agreed upon liquidated delay damages.
Liquidated delay damages are often excluded under the contractual liability exclusion of most CGL policies. The contractual liability exclusion excludes coverage for “liability for which the Insured is obligated to pay damages by reason of the assumption of liability in a contract or agreement.” Courts often find the contractual liability exclusion in a CGL policy precludes coverage for liquidated delay damages, because such damages are contractual in nature and are triggered by the failure to bring the contract to substantial completion by a fixed deadline, regardless of the cause of the delay. However, some courts will look to the cause of the delay and find that there is coverage under a CGL policy for liquidated delay damages that are the result of property damage caused by an accident or occurrence.
In Clark Const. Grp., Inc. v. Eagle Amalgamated Serv., Inc., 01-2478-DV, 2005 WL 2092998, at *1 (W.D. Tenn. Aug. 24, 2005) a general contractor entered a contract for the renovation of the convention center in Memphis. Part of the project included the demolition of a structure attached to the convention center. The demolition work was improperly performed by a subcontractor and resulted in damage to the convention center.
Read the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Tenth Circuit Reverses District Court's Ruling that Contractor Entitled to a Defense
October 24, 2023 —
Tred R. Eyerly - Insurance Law HawaiiAfter the district court granted the insured contractor's motion for judgment on the pleadings on the duty to defend, the Tenth Circuit found there was no coverage and reversed. Owners Ins. Co. v. Greenhalgh Planning & Development, Inc., 2023 U.S. App. LEXIS 20137 (10th Cir. Aug. 4, 2023).
Greenhalgh remodeled a house and barn for Michelle and Steven Pickens. After completion of the project, the Pickens sold the property to Teague and Michelle Cowley. The Cowleys later sued the Pickenses asserting various fraud and breach of contract claims. The complaint alleged that the Pickenses misled them into reasonably believing that the barn was a habitable structure, even though it did not qualify as such under the applicable building code because it lacked a fire-sprinkler system.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com