Arizona Is Smart About Water. It Should Stay That Way.
February 19, 2024 —
Mark Gongloff - BloombergYou really have to hand it to Arizona: Even as its population has doubled and it has suffered through a decades long megadrought, the state uses less water today than it did 40 years ago.
This success story is the result of what may be the smartest, most conservative approach to water in the country. But homebuilders want to scrap some key elements of this careful system. It’s a bad idea, especially as the climate changes, making the state’s water supply less reliable. And it’s a cautionary tale for the rest of us as we try to adapt to a warming world.
In 1980, alarmed at watching its precious groundwater disappear amid rapid development, Arizona passed the Groundwater Management Act. The law established the Arizona Department of Water Resources, set up water-management zones around cities and required new housing developments to prove they had access to 100 years’ worth of clean water, among other things.
Read the full story...Reprinted courtesy of
Mark Gongloff, Bloomberg
Embracing Generative Risk Mitigation in Construction
February 12, 2024 —
Georgia Stillwell - Construction ExecutiveProject delays have long plagued the construction industry, with risk often identified as the primary culprit. However, finding effective solutions to mitigate risk on complex projects has remained daunting. Traditional methods for simulating risk primarily focus on extending project timelines, overlooking the diverse range of opportunities available for risk mitigation. With the construction industry’s digital transformation, generative methodologies have emerged to handle complex decision-making in uncertain situations. This article aims to shed light on the limitations of existing risk modeling and introduce a novel approach known as generative risk mitigation to enhance decision-making under deep uncertainty.
According to McKinsey, 98% of megaprojects experience cost overruns exceeding 30%. Project delays have become so pervasive that the industry has grown accustomed to them. For example, in 2022, the UK government issued ‘
The Green Book,’ which requires contingency funds in projects, such as a 44% contingency budget for standard civil projects. This implies that for a $100 million project, you should allocate $144 million to manage expected risks. There is no denying significant academic literature on the root cause of these delays: it is ‘risk,’ and there is an entire industry based on it.
Conversations with project directors and risk experts reveal the same issue, different project. And that issue is that we cannot easily forecast risk, qualify the impacts or fully understand the opportunities that exist to mitigate risks and make timely decisions. A method that will finally help us overcome this has emerged within the industry.
Reprinted courtesy of
Georgia Stillwell, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
The Contractor’s Contingency: What Contractors and Construction Managers Need to Know and Be Wary Of
December 04, 2023 —
Skyler L. Santomartino - Peckar & Abramson, P.C.Contractors and construction managers who enter into cost reimbursable contracts subject to a guaranteed maximum price (GMP) are responsible for all project costs exceeding the GMP. For this reason, it is imperative that contractors negotiate and incorporate into the GMP a financial buffer that accounts for the unanticipated project costs that are not reimbursable as change orders or costs of the work. This is where the contractor’s contingency comes into play.[
1]
The contractor’s contingency is a vehicle that allows contractors to mitigate some of the risks inherent in GMP contracts. When drafted properly, a contingency clause allows the contractor and only the contractor to access funds set aside by the owner to address unpredictable or unknown project costs.
Read the full story...Reprinted courtesy of
Skyler L. Santomartino, Peckar & Abramson, P.C.Mr. Santomartino may be contacted at
ssantomartino@pecklaw.com
Orange County Team Obtains Unanimous Defense Verdict in Case Involving Failed Real Estate Transaction
March 25, 2024 —
Lewis Brisbois NewsroomOrange County, Calif. (March 4, 2024) - Orange County Partners Esther P. Holm and Alexandra Anast obtained a unanimous defense verdict in a real estate matter involving a failed real estate transaction. The property at issue, which was located in the West Hollywood Hills and had beautiful views, was undergoing extensive remodeling. There were several bids for its purchase. Ultimately, the plaintiff, a real estate investor, was awarded the purchase.
The plaintiff and the seller entered into a real estate purchase agreement, but the plaintiff failed to release the physical contingencies within the 17-day period prescribed by the contract. Instead, the plaintiff demanded a reduction in price, which the seller rejected. The plaintiff then filed a lis pendens on the property, clouding the title and making it impossible for the sellers to sell the property to anyone else. The buyer and seller subsequently engaged counsel. The plaintiff filed the lawsuit against the seller as well as the real estate company and its agents. Prior to trial, the plaintiff and the seller reached a settlement.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Insurer's Motion for Judgment on the Pleadings for Construction Defect Claim Rejected
January 22, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe magistrate judge recommended that the insurer's motion for judgment on the pleadings be denied in a case involving coverage for the insured subcontractor's alleged faulty workmanship. Evanston Ins. Co. v. Sonny Glasbrenner, Inc., 2023 U.S. Dist. LEXIS 190019 (M.D. Fla. Oct. 20, 2023).
Cone & Graham (C&G), the general contractor, subcontracted with Sonny Glasbrenner, Inc. (SGI) to work on the project. The project involved the rehabilitation of a bridge due to deterioration of the existing concrete bridge deck by adding additional cross bracing to further stiffen the steel girders and using special lightweight concrete. C&G contracted SGH to demolish the existing concrete bridge deck. SGI completed the work.
Thereafter, C&G made a demand to SGI for alleged damaged caused by SGI's work. C&G alleged that SGI was negligent in performing the demolition work, causing substantial damage to the existing bridge girders. C&G sued SGI.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New Jersey Court Upholds Registration Requirement for Joint Ventures Bidding on Public Works Contracts
December 16, 2023 —
Nicholas J. Zaita & Brian Glicos - Peckar & Abramson, P.C.Introduction
In a matter of “first impression,” on November 30, 2023, the Appellate Division affirmed the New Jersey Superior Court decision in
Ernest Bock & Sons-Dobco Pennsauken Joint Venture v. Township of Pennsauken and Terminal Construction Corp., finding that the New Jersey Public Works Contractor Registration Act, N.J.S.A. 34:11-56.48 to -56.57 (“PWCRA” or the “Act”), applies to a joint venture formed for the sole purpose of bidding on a public works contract. Therefore, the Court held that the PWCRA requires any joint venture bidding on public works projects in New Jersey to be registered under the Act at the time of bid submission. Accordingly, the Township of Pennsauken acted within its authority and properly rejected the bid submission of the Ernest Bock & Sons-Dobco Joint Venture which was not registered under the Act in the name of the joint venture at the time of its bid submission, despite the individual members of the joint venture being registered.
Reprinted courtesy of
Nicholas J. Zaita, Peckar & Abramson, P.C. and
Brian Glicos, Peckar & Abramson, P.C.
Mr. Zaita may be contacted at nzaita@pecklaw.com
Mr. Glicos may be contacted at bglicos@pecklaw.com
Read the full story...
Partner John Toohey and Senior Associate Sammy Daboussi Obtain a Complete Defense Verdict for Their Contractor Client!
December 11, 2023 —
Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is excited to share that Newport Beach attorneys John Toohey and Sammy Daboussi obtained a complete defense verdict after years-long litigation in favor of their concrete contractor client.
This lawsuit arises from a claim made by Plaintiff for construction defects in a high-end single-family home. Our client was hired to perform concrete work on the foundations of the home. It was alleged that the home’s foundation was incorrectly built. It was further alleged that the construction defects/errors led to delays and substantial expenses. We argued that our client relied on the certifications provided to them by design professionals and the City. We further argued that our client, like any reasonable concrete/foundation subcontractor, has no responsibility or obligation, contractual or otherwise, to review and recheck the work completed by a licensed professional.
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
A Matter Judged: Subrogating Insurers Should Beware of Prior Suits Involving the Insured
March 25, 2024 —
Gus Sara - The Subrogation StrategistIn New Jersey Mfrs. Ins. Co. v. Lallygone LLC, No. A-2607-22, 2024 N.J. Super. Unpub. LEXIS 120, the Appellate Division of the Superior Court of New Jersey (Appellate Division) considered whether New Jersey Manufacturers Insurance Company (the carrier) could bring a subrogation action after its insured, Efmorfopo Panagiotou (the insured), litigated and tried claims related to the same underlying incident with the same defendant, Lallygone LLC (the defendant). The Appellate Division affirmed the trial court’s finding that the prior lawsuit extinguished the carrier’s claims.
In Lallygone LLC, the insured hired the defendant to renovate a detached garage on his property. In March 2022, while the defendant’s employees were removing existing concrete slabs, the garage collapsed. After the incident, the insured stopped paying the defendant. In addition, the insured filed a claim with the carrier, which ultimately paid the insured over $180,000 for the damage under its property policy. The carrier sent a subrogation notice letter to the defendant.