Federal Court Reiterates Broad Duty to Defend in Additional Insured Cases
April 22, 2024 —
Craig Rokuson - Traub LiebermanIn the recent case of
Travelers Indem. Co. of Am. v. Accredited Sur. & Cas. Co., No. 21-CV-7189 (FB) (JRC), 2024 U.S. Dist. LEXIS 44634 (E.D.N.Y. Mar. 13, 2024), the Federal District Court for the Eastern District of New York had occasion to consider an additional insured tender on behalf of a prime contractor, Archstone, to a subcontractor, Topline, who was named as a direct defendant in a New York labor law case. Even though Topline’s carrier put forth evidence that Topline was not negligent, the court held, under New York’s broad duty to defend, that Topline’s carrier owed a duty to defend the prime contractor.
Initially, the court was satisfied that a purchase order, signed only by Topline and not Archstone, was binding on Topline. That purchase order specified that Topline agreed to name Archstone as an additional insured.
With respect to the duty to defend, the court found that it was enough that the underlying plaintiff alleged that all defendants, including Topline, were negligent in permitting a ladder that plaintiff was on to remain in a defective condition and in failing to foresee the existence of a hazard from the condition of the subject ladder.
Read the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
Emerging Trends in Shortened Statutes of Limitations and Statutes of Repose
January 02, 2024 —
Ivette Kincaid & Thomas McCarrick - Kahana FeldIntroduction
A growing trend in construction defect legislation around the country has seen the shortening of statutes of limitation and statutes of repose for a plaintiff to bring claims related to construction defects. Over the past ten years, several states, notably Florida and Texas, have shortened their statutes of repose. This is generally positive news for developers and contractors; however, the specifics and ramifications of these legislative and judicial updates are still unknown.
Statute of Limitations
A statute of limitations sets forth the time that a plaintiff has to sue or allege a particular cause of action against a defendant. These time limitations are codified into law and vary depending on the State and the cause of action. A statute of limitations starts at the occurrence of an injury or damage or at the time the injury or damage is discovered. The statute of limitations may be subject to some exceptions such as tolling for reasons such as the injured party being a minor in which case depending on the particular statute, the statute does not begin to run until after the minor reaches the age of majority.
Reprinted courtesy of
Ivette Kincaid, Kahana Feld and
Thomas McCarrick, Kahana Feld
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Mr. McCarrick may be contacted at tmccarrick@kahanafeld.com
Read the full story...
Washington’s Court of Appeals Protects Contracting Parties’ Rights to Define the Terms of their Indemnity Agreements
March 19, 2024 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIt has long been the law in Washington that contracting parties are free to draft contractual indemnity agreements to allocate risk arising from performance of the work, and Courts will generally enforce those agreements as written. This well-settled principle was recently reaffirmed in King County v. CPM Development Corp., dba ICON Materials[1] a decision from Division I of the Washington Court of Appeals, wherein one party to an indemnity agreement attempted to evade its contractual obligations by arguing that certain common law indemnity principles supersede the written terms. This appeal followed a multi-week jury trial from which the client and Ahlers Cressman and Sleight legal team, including Lindsay Watkins, Klien Hilliard, and Christina Granquist, obtained a seven-figure judgment in the client’s favor, including an award of all attorneys’ fees and costs.
ICON was the general contractor on a Vashon Island Highway Pavement project for King County. Part of the work on the project involved hauling away and disposing of ground milled asphalt (the “millings”) at King County-approved sites. ICON and D&R Excavating Inc., (“D&R”) executed a subcontract for D&R to perform that work. The subcontract incorporated the contract between ICON and King County, including the obligation to stockpile millings only at approved sites. D&R, however, did not obtain the requisite approvals from King County, and placed the millings at various sites on the Island, including locations that King County explicitly rejected.
Read the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
Penalty for Failure to Release Expired Liens
April 02, 2024 —
William L. Porter - Porter Law GroupI was recently contacted by a commercial building owner in the process of trying to sell his building. Two years prior to this, a subcontractor had recorded a mechanics’ lien with the local County Recorder’s office in relation to the owner’s property. The subcontractor recorded the mechanics lien after the subcontractor was not paid by a prime contractor for work the subcontractor had performed on the property. Unfortunately, the subcontractor then failed to file a lawsuit to foreclose on the lien within the requisite ninety (90) day time period for filing a lawsuit to foreclose on the mechanics’ lien. Since the subcontractor missed this 90 day deadline to file the mechanics lien foreclosure lawsuit, the mechanics lien expired and became unenforceable.
Subject to certain exceptions, under California Civil Code Section 8460, a lawsuit to foreclose on a mechanics lien must be filed within ninety (90) days after the mechanics lien is recorded or the mechanics lien expires. Although the mechanics lien had expired, the title company and intended purchaser of the building and property were perhaps understandably insistent that the mechanics lien constituted a cloud on title to the property and must be removed from the official records for the property. The prospective purchaser would not buy the property unless the mechanics’ lien was removed.
Read the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
The Sounds of Silence: Pennsylvania’s Sutton Rule
January 29, 2024 —
William L. Doerler - The Subrogation StrategistIn Westminster Am. Ins. Co. a/s/o Androulla M. Toffalli v. Bond, No. 538 EDA 2023, 2023 Pa. Super. LEXIS 626, 2023 PA Super 272, the Superior Court of Pennsylvania (Appellate Court) recently discussed the impact of silence on the Sutton Rule with respect to the landlord, Androulla M. Toffalli (Landlord), securing insurance. After holding that the tenant, Amy S. Bond (Bond) t/a Blondie’s Salon – who leased both commercial and residential space in the building pursuant to written leases – was not an implied “co-insured” on Landlord’s insurance policy, the Appellate Court reversed the decision of the trial court.
In this case, Bond rented the ground floor of a property located in Monroe County pursuant to a written commercial lease (Commercial Lease) and operated Blondie’s salon out of the leased location. In addition, Bond rented and lived in a second-floor apartment pursuant to a residential lease (Residential Lease). Both leases required the tenants (Tenants) to obtain insurance for personal items. The leases, however, did not require Landlord to obtain fire insurance for the property.
Read the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Surplus Lines Carrier Can Force Arbitration in Louisiana Despite Statute Limiting Arbitration
February 12, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the surplus lines insurer's motion to compel arbitration despite a Louisiana statute barring policies from depriving courts of jurisdiction in cases against insurers. Queens Beauty Supply, LLC v. Indep.Specialty Ins. Co., 2023 U.S. Dist. LEXIS 195372 (E.D. La. Oct. 31, 2023).
Hurricane Ida damaged property leased by Queens. Queens filed suit against its insurer, Independent Specialty Insurance Company (ISIC) for breath of contract and bad faith for failing to pay the full amount Queens contends it was owed for the damage. ISIC moved to compel arbitration.
Queens argued that ISIC waived its right to enforce the policy's arbitration clause by its actions before the court, including failing to opt-out of the settlement program adopted for Hurricane Ida cases. The court disagreed, ISIC had taken no overt act that evidenced a desire to resolve the instant dispute through litigation rather than arbitration. ISIC asserted as an affirmative defense that Queens's claims were barred by the arbitration clause in the policy. ISIC then participated in the settlement program for Hurricane Ida cases, which evidences a desire to settle the dispute, not to resolve it by litigation. Therefore, ISIC had not waived its right to arbitrate.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Johnstown Dam Failure, as Seen in the Pages of ENR in 1889
April 08, 2024 —
Scott Lewis - Engineering News-RecordThe small headline of the Engineering News article shown here belies the gravity of the disaster: the deadliest dam failure in U.S. history. The South Fork Dam in Pennsylvania was a 72-ft-tall, 931-ft long earth and rockfill structure. After a stop-and-start construction process over a dozen years, it was completed in 1853. The dam went through several changes of ownership and was repaired inadequately. Fish screens were installed that obstructed the spillway and caused water to overtop and erode the structure. This mass of water uprooted trees, rocks, houses, rail cars and animals as it thundered down the valley before smashing into a stone railway embankment. Fires ignited by wrecked locomotives burned for three days. The death toll was 2,208.
Reprinted courtesy of
Scott Lewis, Engineering News-Record
Mr. Lewis may be contacted at lewisw@enr.com
Read the full story...
Court Grants Insurer's Motion for Summary Judgment After Insured Fails to Provide Evidence of Systemic Collapse
April 15, 2024 —
Tred R. Eyerly - Insurance Law HawaiiWith the insurer conceding that there was evidence of potential collapse at portions of eight specific building locations, the court granted the insurer's motion for partial summary judgment in determining no additional buildings suffered from collapse. Exec. 1801 LLC v. Eagle W. Ins. Co., 2024 U.S. Dist. LEZXIS 5923 (D. Or. Jan. 11, 2024).
Executive 1801 owned a group of six buildings with eighty-six residential units. The court previously granted partial summary judgment on Executive 1801's rain damage claim, leaving only claims regarding collapse. Eagle insured "the property for direct physical los or damage to Covered Property . . . caused by or resulting from any Covered Cause of loss." The policy further provided, "We will pay for direct physical loss or damage to Covered Property, caused by collapse of a building or any part of a building insured under this policy, if the collapse is caused by . . . hidden decay."
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com