“Bound by the Bond”
September 02, 2024 —
Daniel Lund III - LexologyA New York trial court granted judgment in favor of a performance bond surety on a construction project, based upon the failure of the claiming party to abide by the terms of the bond.
The “AIA Document A312” bond form – described by the court (quoting surety law authority) to be “one of the clearest, most definitive, and widely used type of traditional common law ‘performance bonds’ in private construction” – contains various procedures which must be honored as a “condition precedent to an action to recover” on the bond/against the surety. One of those prerequisites is a “declaration of default” concerning the contractor principal (here, a subcontractor).
The case involved the construction of an 85-story skyscraper in midtown Manhattan, and the performance of the subcontract for the building’s superstructure. The bonded contract was at a value of approximately $25,000,000 and obligated the sub to provide a performance bond “in a form similar to the [A312 bond],” and which was otherwise satisfactory to the obligee/construction manager.
Read the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Timely and Properly Assert Affirmative Defenses and Understand Statutory Conditions Precedent
August 05, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent case serves as a reminder to TIMELY and PROPERLY assert affirmative defenses and to understand statutory conditions precedent to construction lien claims. Failing to do one or the other could be severely detrimental to the position you want to take in a dispute, whether it is a lien foreclosure dispute, or any other dispute.
In Scherf v. Tom Krips Construction, Inc., 2024 WL 3297592 (Fla. 4th DCA 2024), the president of a construction company and his wife were building a residence. They orally accepted the proposal from the concrete shell contractor and asked for invoices to be submitted to the president’s construction company. No written contract was memorialized. The president and his wife did not pay the concrete shell contractor and the contractor recorded a lien and sued to foreclose on the lien. Years later (the case had been stayed because the president and his wife filed for bankruptcy and the shell contractor had to get leave of the automatic bankruptcy stay to pursue the lien foreclosure), the shell contractor moved for summary judgment. The president and his wife moved for leave to file an amended answer and affirmative defenses. They claimed the oral contract was with the construction company and the shell contractor was required to serve a Notice to Owner under
Florida Statute s. 713.06. Alternatively, they argued that if the oral contract was with the president and his wife, the shell contractor was required to serve a Final Contractor’s Payment Affidavit at least 5 days before filing its lien foreclosure claim, and did not, as required by s. 713.06.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
New Mexico Holds One-Sided Dispute Resolution Provisions Are Unenforceable
November 05, 2024 —
Bill Wilson - Construction Law ZoneDispute resolution provisions that grant one party the unilateral right to choose either litigation or arbitration to resolve disputes are common in the construction industry. The main difference between the two forums is that courts are more likely to strictly enforce contract terms as written as well as the applicable law, while arbitrators make decisions on more equitable considerations, untethered to the contract terms and—to some degree—the law. The party with the sole discretion to select the dispute resolution procedure can select the process most beneficial to its interests based on the nature of the dispute, regardless of who brings the claims. In Atlas Electrical Construction, Inc. v. Flintco, LLC, 550 P.3d 881 (N.M. Ct. App. 2024), the Court of Appeals of New Mexico recently held that an arbitration provision in a subcontract, under which the contractor retained the exclusive right to choose whether disputes arising under the subcontract were litigated in court or arbitrated was unreasonably one-sided, substantively unconscionable, and unenforceable.
The Atlas Electrical case involved two sophisticated entities with equal bargaining strength to negotiate the terms of a subcontract. The parties agreed to a subcontract provision which provided in the relevant part:
In the event [contractor] and [subcontractor] cannot resolve the dispute through direct discussions or mediation … then the dispute shall, at the sole discretion of [contractor], be decided either by submission to (a) arbitration … or (b) litigation …
Read the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Construction of World's Tallest Building to Resume With New $1.9B Contract for Jeddah Tower
October 28, 2024 —
James Leggate - Engineering News-RecordConstruction of the Jeddah Tower in Jeddah, Saudi Arabia—which is planned to be the world’s tallest building—is set to resume with original contractor Saudi Binladin Group Co. after a years-long pause, owner Jeddah Economic Co.'s parent company, Kingdom Holding Co., announced Oct. 2.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story...
“Since You Asked. . .”
October 15, 2024 —
Daniel Lund III - Lexology… you must now pay.
So said a California appellate court, affirming the trial court’s decision against a subcontractor suing for unpaid subcontract sums. Instead of being awarded those unpaid amounts, the subcontractor lost the case and was tagged with a $1.55 million attorney’s fees award and $270,000 costs award in favor of the defendants.
What went wrong?
California law requires a licensed contractor to maintain at all times proper workers’ compensation insurance coverage. The failure to maintain the coverage and have the certificate of coverage on file with the California Contractors State License Board results in “automatic and immediate suspension” of the contractor license. Retroactive reinstatement of the license may occur only if the contractor provides proof of the insurance within 90 days of the effective date of the insurance certificate – unless the contractor can show that failure to have the certificate on file was “due to circumstances beyond the control of the licensee.”
Read the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Deferred Maintenance?
December 17, 2024 —
Daniel Lund III - LexologyA Tennessee-based “outsourced maintenance vendor” to an engine company filed suit in Louisiana state court seeking to recover nearly $150,000 on “open account,” for work previously performed. The engine company removed the case to the Federal District Court in New Orleans and asserted as a defense that the vendor lacked a proper Louisiana construction contractor’s license. The engine company filed a motion for summary judgment based on the defense.
Under Louisiana law, a contract between parties is “absolutely null”--considered to have never existed--where one of the parties performed services without a required Louisiana contractor’s license, and the combined work reaches a $50,000 threshold. The engine company asserted that the vendor performed typical construction contractor work, including plywood flooring, applied epoxy to concrete flooring, erected part of a commercial carport, undertook certain heavy demolition, and installed fences, guardrails, and wire racks.
Read the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
A “Flood” of Uncertainty; Massachusetts SJC Finds Policy Term Ambiguous
August 26, 2024 —
Michael S. Levine & Torrye Zullo - Hunton Insurance Recovery BlogThe highest court in Massachusetts recently held that term “Flood” and the associated phrase “surface waters,” as used in two all-risk insurance policies, is ambiguous in the context of water that accumulated on a parapet roof and rooftop courtyard, thereby negating the insurers’ attempt to limit coverage to a sublimited coverage for “Flood.”
Background
In June 2020, a severe storm caused damage to Norwood Hospital, owned by Medical Properties Trust, Inc. (“MPT”) and leased to Steward Health Care System (“Steward”), the policyholders. The relevant portion of the damage included damage from rain that accumulated on the rooftop courtyard and seeped into the interior of the building causing damage to the building and its contents.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Torrye Zullo, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Zullo may be contacted at tzullo@HuntonAK.com
Read the full story...
Real Estate & Construction News Roundup (7/10/24) – Strong Construction Investment in Data Centers, Increase Use of Proptech in Hospitality and Effects of Remote-Work on Housing Market
August 05, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, renters stay in their units longer, GenAI change how commercial real estate operates, and banks continue high exposure due to commercial real estate.
- Strong investor interest, particularly in opportunistic and value-add segments, signals a strong market for construction firms specializing in high-yield projects. (Sebastian Obando, Construction Dive)
- A growing number of renters are staying in their units for longer periods of time than they did a decade ago with over one-third of U.S. renters have lived in the same apartment for more than five years. (Mary Salmonsen, Multifamily Dive)
- Several U.S. regional and mid-sized banks continue to face the squeeze from high exposure to the commercial real estate sector that has been shaken by higher-for-longer interest rates and empty office buildings. (Reuters)
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team