Recovering Time and Costs from Hurricane Helene: Force Majeure Solutions for Contractors
November 18, 2024 —
Matthew DeVries - Best Practices Construction LawWhen Hurricane Helene struck North Carolina, it caused severe disruptions to construction projects across the state. Baxter International’s North Cove facility in Marion, N.C., was completely shut down after floodwaters damaged the site and bridges leading to it. Elsewhere, landslides and floods wiped out large sections of Interstate 40, making transportation of materials and equipment nearly impossible. Many contractors in western North Carolina found their projects halted, and their schedules thrown off by this force majeure event.
In situations like these, contractors and subcontractor need a plan to mitigate the impact of such natural disasters on their projects. Here are five practical tips to help you secure time extensions and/or compensation for delays:
1. Include a Robust Force Majeure Clause in Your Contract
When disaster strikes, your contract is your first line of defense. A well-drafted force majeure clause can make the difference between bearing the costs yourself and getting an extension or compensation. The clause should clearly list specific events such as hurricanes, floods, and road closures as qualifying force majeure events.
Read the full story...Reprinted courtesy of
Matthew DeVries, BuchalterMr. DeVries may be contacted at
mdevries@buchalter.com
New Research Shows Engineering Firms' Impact on Economy, Continued Optimism on Business Climate
October 28, 2024 —
The ACEC Research InstituteWASHINGTON – The ACEC Research Institute – the leading source of original research for the business of engineering – released the results of two important studies on the current and future state of the engineering industry, and its role in the overall U.S. economy.
The reports, the
2024 Economic Assessment of the Engineering & Design Services Industry and the
Engineering Business Sentiment Report for 2024 Q4, both point to continued optimism for the industry and its firms, though somewhat softened compared to previous quarters.
"This research shows the outsized impact the engineering industry has on the American economy," said ACEC Research Institute Chair Mike Carragher. "As the engineering industry's contributions grow year over year, the Institute's research helps firm executives position their businesses for a successful future."
All told, the industry added $656 billion to the U.S. GDP in 2023, supported well over five million jobs directly or indirectly, and contributed $92 billion to federal tax coffers, with an additional $44 billion in state and local taxes.
Overall, the report found that the engineering and design services industry has continued to build on its year-over-year post-COVID gains, growing 5.5% in 2023 to $436 billion, with much of that growth driven by infrastructure projects. Non-residential and non-building construction, flush with government funding through the IIJA and Inflation Reduction Act, remained on an upward trajectory.
Report Highlights Trends in Construction Tech, Digitization, and AI
November 11, 2024 —
Aarni Heiskanen - AEC BusinessBluebeam, a top technology provider for AEC professionals, has just released its “Building the Future: Bluebeam AEC Technology Outlook 2025” report. This report highlights key global trends in construction technology, including the role of AI and digital tools. Based on insights from over 400 AEC technology leaders, the report also uncovers challenges that prevent full-scale adoption of these tools.
The online research surveyed technology decision-makers (managers or above) within AEC firms in the US, UK, Canada, France, Spain, Germany, Australia, and New Zealand in July 2024.
AI’s Growing Role in Construction
According to the report, 74% of surveyed AEC professionals are now using AI in one or more phases of building projects. AI is especially popular in the design (48%) and planning (42%) stages. Many AEC firms recognize its value: over half (55%) of companies using AI say it’s crucial, and most now allocate up to 25% of their budgets to AI initiatives. Despite this support, concerns over AI regulation are significant. About 54% of respondents are worried about regulations, and 44% say this impacts their use of AI.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
The Privette Doctrine and Its Exceptions: Court of Appeal Grapples With the Easy and Not So Easy
November 18, 2024 —
Garret Murai - California Construction Law BlogIn
CBRE v. Superior Court, 102 Cal.App.5th 639 (2024), the 4th District Court of Appeal grappled with a thorny and not-so-thorny issue involving injured parties under the Privette doctrine. The less thorny issue was whether application of the Privette doctrine depends on whether a written contract exists between the parties. Spoiler: It does not. The thorny issue was whether the Hooker exception to the Privette doctrine – which applies when a landowner exercises control over a project – should apply where a landowner directs a contractor to perform work that is at odds with legal requirements.
The CBRE Case
Property Reserve, Inc. owns an office building managed by CBRE in San Diego, California. On April 9, 2019, PRI entered into a lease agreement with a new tenant for a suite in the building. The lease required that PRI perform certain tenant improvements.
Read the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Protecting Expert Opinions: Lessons Regarding Attorney-Client Privilege and Expert Retention in Construction Litigation
August 19, 2024 —
David McLain - Higgins, Hopkins, McLain & Roswell, LLCThe Hill Hotel Owner LLC v. Hanover Insurance Company case has garnered attention due to its implications on the scope of attorney-client privilege in construction litigation. This blog post delves into the project’s background, the ensuing litigation, and the intricate work undertaken by attorneys and experts, highlighting the potential pitfalls associated with assumptions about privilege protections.
Background of the Project
Hill Hotel Owner LLC initiated a construction project in Boulder, Colorado, which included building a basement-level parking garage with an 18” thick concrete slab floor. The project utilized “void form,” a cardboard underlayment intended to create a gap between the foundation and the underlying soil. Unfortunately, the void form became wet and collapsed under the weight of the fresh concrete, causing considerable damage, and necessitating millions of dollars in remediation costs.
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
For US Cities in Infrastructure Need, Grant Writers Wanted
July 22, 2024 —
Patrick Sisson - BloombergIt’s a big windfall of federal investment. Together, bills like the Inflation Reduction Act, the Bipartisan Infrastructure Law, and the CHIPS Act present a substantial shift in how the US government funds local economic development, clean energy and environmental justice efforts, potentially giving cities and towns a huge boost.
That is, if the nation’s 90,000-plus municipalities and tribal governments can finish filling out all the paperwork.
The trillion-dollar trifecta of Biden administration legislation from 2022 underscores just how important grant writing has become. In many ways, the ability of cities to enact new policies and tap federal resources rests on the desks of the staffers or contract workers who research, write and submit applications for funding. Uncle Sam will cheerfully write a check for cities to install solar panels via Clean Electricity Investment and Production Tax Credits, for example, or provide tax credits for buying electric vehicles. But first, you have to ask.
Read the full story...Reprinted courtesy of
Patrick Sisson, Bloomberg
Updates to AIA Contract Applications
January 07, 2025 —
Anand Gupta - Construction Law Zone BlogThe construction industry often relies on contract forms drafted by the American Institute of Architects (AIA). These AIA forms include agreements between owners, designers, consultants, contractors, subcontractors, and construction managers. Some prefer to use the forms in the stock form, but others prefer to modify the language to their benefit. These modifications can be made in Microsoft Word and uploaded into AIA’s current web-based system, ACD5, to create redlines against the standard AIA forms (Checked-Drafts) and final clean versions without the “DRAFT” watermarks. Law firms and clients keep repositories of these modified templates for future projects.
A common issue with modifying documents offline in Microsoft Word and passing the documents back-and-forth between different email and document management systems is that the metadata of the forms becomes corrupted. AIA technical support then must reset the metadata, which takes hours or days. This delay can pose challenges to clients when they are up against a deadline.
Read the full story...Reprinted courtesy of
Anand Gupta, Robinson+ColeMr. Gupta may be contacted at
agupta@rc.com
Slow Down?
December 03, 2024 —
Daniel Lund III - LexologyAbsolutely not, said the Louisiana Fifth Circuit Court of Appeal to a masonry subcontractor being sued for allegedly improperly refusing to honor a subcontract bid.
A general contractor preparing its overall bid for a public project in Jefferson Parish relied in the process on the defendant masonry subcontractor’s bid. After a public bid process and receiving the award of the project, the general contractor was informed by the subcontractor that it believed that the unit price form that had been supplied to the sub “contained inaccuracies.” Notwithstanding offers by the GC to endeavor to address the purported “inaccuracies” during the project, most likely by a change order, the subcontractor refused to execute its subcontract. The general contractor then awarded the masonry work to another subcontractor for $368,222 more than the original sub’s bid.
The GC filed suit – for recovery of $368,222 – against the defendant subcontractor during the course of the public project. The defendant sub objected, arguing to the court that the lawsuit was “premature.” At the heart of the prematurity argument: the sub urging that the general contractor filed suit before its right to recover damages had accrued.
Read the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com