PJM’s Reliability Backstop Procurement Proposal—Fast-Track Capacity to Meet Rising Large-Load Demand
May 12, 2026 —
Stephen J. Humes, Alicia M. McKnight, Jason Drogin Atwood & Andrew H. Jacobs - Gravel2GavelIn January, we discussed the Statement of Principles jointly signed by the National Energy Dominance Council and governors across the mid-Atlantic region—framing accelerating demand (especially from large-scale data centers) as an emergency reliability issue for PJM Interconnection, L.L.C. (PJM), the nation’s largest power grid operator. That policy signal is now becoming a near-term, accelerated procurement and contracting exercise. On April 8, 2026, PJM notified stakeholders of a critical issue fast path reliability backstop procurement process. PJM subsequently released a request for information (RFI) with respect to a proposed Reliability Backstop Procurement (RBP)—a one-time mechanism intended to attract significant new capacity to address projected reliability shortfalls driven by large-load growth.
RBP compresses what is often a multiyear market and regulatory conversation into a fast-moving set of commercial choices. Developers, large loads, utilities and capital providers should be preparing now for (i) an accelerated bilateral contracting window and (ii) a standardized PJM-led backstop procurement if bilateral deals do not clear enough capacity.
Reprinted courtesy of
Stephen J. Humes, Pillsbury,
Alicia M. McKnight, Pillsbury,
Jason Drogin Atwood, Pillsbury and
Andrew H. Jacobs, Pillsbury
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. McKnight may be contacted at alicia.mcknight@pillsburylaw.com
Mr. Atwood may be contacted at jason.atwood@pillsburylaw.com
Mr. Jacobs may be contacted at andrew.jacobs@pillsburylaw.com
Read the full story...
Building in Arizona’s Data Center Boom: How Federal Executive Orders, State Regulation, and National-Security Policy Are Reshaping the Rules for Developers
June 02, 2026 —
Ryan J. Regula - Snell & WilmerDevelopers and practitioners evaluating data center projects in Arizona face a regulatory environment shifting on three fronts simultaneously. Federal executive orders are opening new land, streamlining permitting, and channeling financial incentives toward qualifying projects — but they are not preempting the state and local rules that most directly affect project economics. A carve-out in the December 2025 Artificial Intelligence (AI) Framework Executive Order preserves Arizona’s authority over data center infrastructure, meaning the Arizona Corporation Commission’s (ACC) rate-classification docket, municipal zoning restrictions, water-use ordinances, and pending grid cost-allocation legislation remain the binding constraints on project feasibility. Understanding where federal tailwinds end and state and local headwinds begin is essential for any developer sizing risk or selecting sites in the state.
The Federal Landscape: An Interlocking Framework of Executive Orders
Five interlocking executive orders are accelerating data center development nationally, but none overrides Arizona’s authority over siting energy, or infrastructure.
Read the full story...Reprinted courtesy of
Ryan J. Regula, Snell & WilmerMr. Regula may be contacted at
rregula@swlaw.com
Snell & Wilmer’s Los Angeles Office Recognized as One of the “Best Places to Work” by the Los Angeles Business Journal
September 15, 2026 —
Snell & WilmerLOS ANGELES – Snell & Wilmer is proud to announce that its Los Angeles office has been named one of the
2026 Best Places to Work by the Los Angeles Business Journal as part of its annual Best Places to Work awards. The recognition honors outstanding employers across the Los Angeles region that are fostering strong workplace cultures and creating positive employee experiences. Selections are based on confidential employee surveys conducted by Workforce Research Group, which evaluate organizations on leadership, corporate culture, communication, employee engagement, and other key workplace factors.
“We are honored to be recognized as one of the Best Places to Work in Los Angeles,” said
Joshua Schneiderman, managing partner of the firm’s Los Angeles office. “This recognition reflects the collaborative culture we have built and the dedication of our attorneys and professional staff who contribute to making our office a great place to work. We remain committed to providing opportunities for growth, fostering meaningful connections, and supporting our team members’ continued success.”
Read the full story...Reprinted courtesy of
Snell & Wilmer
Southwest Super Lawyers Recognizes 50 Snell & Wilmer Attorneys in 2026 Rankings
June 15, 2026 —
Snell & WilmerPHOENIX (April 22, 2026) – Snell & Wilmer is pleased to announce that 50 attorneys in the Phoenix and Tucson offices have been selected for inclusion in the 2026 Southwest Super Lawyers publication. Of those 50, four were recognized for the first time and 24 were recognized as Southwest Rising Stars. Super Lawyers is a listing of lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The selection process is multi-phased and includes independent research, peer nominations, and peer evaluations. Super Lawyers was first published in 1991 by Law & Politics and was acquired by Thomson Reuters, Legal in February 2010. Thomson Reuters is a leading source of information for businesses and professionals. The below Snell & Wilmer attorneys have been selected for inclusion in the 2026 Southwest Super Lawyers rankings.
Read the full story...Reprinted courtesy of
Snell & Wilmer
The GKN Aerospace Chemical Release and the Laws Designed to Address It
July 06, 2026 —
Sean M. Sherlock - Snell & WilmerOn May 21, 2026, a 34,000-gallon storage tank at the GKN Aerospace facility in Garden Grove, California began leaking methyl methacrylate (MMA), a volatile and highly flammable industrial chemical used to manufacture high-strength acrylic plastics. GKN Aerospace makes advanced military and commercial transparencies, such as aircraft canopies, windshields, cabin windows, bullet-resistant glass, and spacecraft windows.
In polymer chemistry lingo, MMA is known as a monomer. Monomers are like individual links to a chain. Under the right conditions they link up (react) with each other to form long-chained polymers, or plastics. MMA is an unstable monomer that requires controlled storage conditions to avoid setting off a polymerization (chain) reaction.
According to early reports, the MMA tank at GKN Aerospace overheated. The cause of the overheating is not yet clear, but the overheating may have created conditions enabling the MMA to initiate polymerization, which in turn generated heat, which in turn generated pressure, activating the tank’s pressure-relief system and releasing MMA vapor into the atmosphere. Concerns about a runaway reaction, massive release, and explosion led the Orange County Fire Authority to order evacuation of approximately 40,000 residents and closure of thirteen schools.
Read the full story...Reprinted courtesy of
Sean M. Sherlock, Snell & WilmerMr. Sherlock may be contacted at
ssherlock@swlaw.com
Snell & Wilmer’s San Diego Office Ranked #1 “Best Place to Work” by the San Diego Business Journal
September 01, 2026 —
Snell & WilmerSAN DIEGO – Snell & Wilmer is proud to announce that its San Diego office has been named the
#1 Best Place to Work in the Large Business category by the San Diego Business Journal as part of its
2026 Best Places to Work awards. The annual recognition honors outstanding employers across the San Diego region that are setting the standard for workplace culture and employee engagement. Rankings are based on confidential employee surveys conducted by Workforce Research Group, which evaluate organizations on leadership, corporate culture, communication, employee engagement, and other key workplace factors.
“Being recognized as the #1 Best Place to Work in the Large Business category is an incredible honor because it reflects the experiences and feedback of our own team,” said
Bardia Moayedi, managing partner of Snell & Wilmer’s San Diego office. “Our people are the foundation of everything we do, and this recognition speaks to the collaborative, inclusive, and supportive culture they have helped create. I am grateful to every member of our San Diego office for making this an exceptional place to build a career, serve our clients, and give back to our community.”
Read the full story...Reprinted courtesy of
Snell & Wilmer
Course of Construction Exclusions and the CGL Policy
July 20, 2026 —
Anna M. Perry, Rachel S. Kindseth & Nina Catanzaro - Saxe Doernberger & Vita, P.C.I. Course of Construction Exclusions
Course of Construction (“COC”) exclusions are found on General Liability and excess liability policies, typically a wrap-up or project specific policy, and generally exclude “all property damage occurring during the course of construction.” Insurers claim COC exclusions are not problematic because they are intended to prevent an overlap in coverage between the general liability policy and first-party property Builder’s Risk policy. However, because General Liability policies and Builder’s Risk policies provide coverage for different risks, COC exclusions can create a gap in coverage for owners and contractors. Therefore, any exclusion on a wrap-up or project specific policy that limits coverage for property damage liability should be scrutinized, and amendments sought when warranted and commercially achievable, for owners, developers and contractors because General Liability policies do not cover the same risk as that of a Builder’s Risk policy.
General liability policies provide defense and indemnity to the insured(s) for claims made by a third-party against the insured. Broad COC exclusions serve to preclude coverage for all property damage, not just property damage to the insured project. This includes property damage to property other than the insured project, e.g. an adjacent property. On the other hand, Builder’s Risk policies provide first-party property coverage for direct physical loss to the project during the course of construction. The Builder’s Risk policy will not provide coverage for property other than the project itself (e.g., adjacent property) and it will not provide a defense or indemnity in the event the owner of the damaged property brings a claim against a potentially at-fault party.
Reprinted courtesy of
Anna M. Perry, Saxe Doernberger & Vita, P.C.,
Rachel S. Kindseth, Saxe Doernberger & Vita, P.C. and
Nina Catanzaro, Saxe Doernberger & Vita, P.C.
Ms. Perry may be contacted at APerry@sdvlaw.com
Ms. Kindseth may be contacted at rkindseth@sdvlaw.com
Ms. Catanzaro may be contacted at NCatanzaro@sdvlaw.com
Read the full story...