Compliance Doesn’t Pay: Compliance Evidence Inadmissible in Strict Liability Actions
February 05, 2024 —
Kyle Rice - The Subrogation StrategistIn Sullivan v. Werner Co., No. 18 EAP 2022, 2023 Pa. LEXIS 1715 (Dec. 22, 2023), the Supreme Court of Pennsylvania (Supreme Court) clarified that in light of its decision in Tincher v. Omega Flex, Inc., 628 Pa. 296 (2014), evidence that a product complied with industry standards is inadmissible in an action involving strict product liability.
In Tincher, the Supreme Court overruled prior case law and reaffirmed that Pennsylvania is a Second Restatement Jurisdiction. As stated in Sullivan, discussing Tincher, under the Restatement (Second) of Torts § 402A, a “seller of a product has a duty to provide a product that is free from ‘a defective condition unreasonably dangerous to the consumer or [the consumer’s] property.’ To prove breach of this duty, a ‘plaintiff must prove that a seller (manufacturer or distributor) placed on the market a product in a “defective condition.””
Read the full story...Reprinted courtesy of
Kyle Rice, White and WilliamsMr. Rice may be contacted at
ricek@whiteandwilliams.com
6 Ways to Reduce Fire Safety Hazards in BESS
January 02, 2024 —
The Hartford Staff - The Hartford InsightsRenewable energy sources, such as solar and wind, are projected to generate 44% of all power in the U.S. by 2050, which is increasing the need for battery energy storage systems (BESS).1
BESS are electrochemical devices that collect energy from a power grid, power plant or renewable source, hold it, and then discharge that energy later to provide electricity on demand.
“A BESS does not itself create or produce energy, it is a storage system. The energy is produced by other means, including different types of renewable sources. Think of a cellphone – you charge it overnight and then it runs throughout the day off that battery power,” says Stacie Prescott, head of energy for middle and large commercial at The Hartford.
Read the full story...Reprinted courtesy of
The Hartford Staff, The Hartford Insights
Stay of Coverage Case Appropriate While Court Determines Arbitrability of Dispute
April 22, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Fifth Circuit vacated a discovery order issued by the district court and remanded the case for issuance of a stay while the arbitrability of the coverage dispute was reviewed. Cameron Parish Recreation #6 v. Indian Harbor Ins. Co., et al., 2024 U.S. App. LEXIS 3804 (5th Cir. Feb. 19, 2024).
The plaintiffs purchased surplus lines polices from various insurance companies to provide coverage for commercial properties. The policies included an arbitration provision for resolving any disputes. After plaintiffs were denied coverage for damage to their properties from Hurricane Laura, they sued the insurers. The insurers filed motions to compel arbitration and to stay the case. The district court refused the stay and ordered limited discovery into arbitrability. The insurers appealed.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Missouri Protects Subrogation Rights
April 15, 2024 —
Lian Skaf - The Subrogation StrategistThe point at which an insurance carrier possesses the equitable right of subrogation is an issue on which the states have differed. Some allow carriers to pursue rights of subrogation immediately upon payment and some have taken stricter approaches. Missouri falls into the latter group. By not allowing the carrier the right to file suit against third-party tortfeasors until the insured provides its carrier with an assignment of all its rights, Missouri’s approach has opened the door for challenges to subrogation rights.
In Megown v. Auto Club Fam. Ins. Co., 2024 Mo. App. LEXIS 82, the plaintiff-insureds Michael and Jane Megown (the Megowns) suffered a house fire on February 8, 2016. Their insurance carrier, Auto Club Family Insurance Company (Auto Club) reimbursed the Megowns for their property damage in the amount of $722,433.56. Subsequently, the Megowns sued Auto Club for breach of contract and later amended their complaint to add claims against Tyberius Enterprises, LLC d/b/a Crag Electric (Craig Electric), the third-party tortfeasor, for direct negligence, alleging both property damage and personal injuries. Auto Club intervened in the Megowns’ claim against Craig Electric to protect its interest as subrogee for its property damage payment to the Megowns. Craig Electric settled prior to trial, paying $1,000,000.00 to both the Megowns and Auto Club, to be allocated at a later date. After a bench trial that apportioned the settlement with $722,433.56 paid to Auto Club and $277,566.44 paid to Megowns – and a jury trial awarding no further damages – the Megowns appealed.
Read the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Compliance with Contractual and Jurisdictional Pre-Suit Requirements is Essential to Maximizing Recovery
November 27, 2023 —
Michael S. Levine, Geoffrey B. Fehling & Charlotte Leszinske - Hunton Insurance Recovery BlogTimely notice is an important first step in a successful insurance recovery. But insurance policies are not always straightforward in identifying how, when, and to whom notice must be provided. Some states may also impose additional procedural hurdles, including requiring policyholders to contact their insurers before filing suit (the idea behind this requirement is that it may avoid litigation). Failing to comply with pre-suit requirements can hurt the policyholder’s recovery, as illustrated in a recent decision from the Northern District of Texas.
In NewcrestImage Holdings, LLC v. The Travelers Lloyds Insurance Company, No. 2:23-cv-039-BR (N.D. Tex. Oct. 17, 2023), the court considered whether NewcrestImage had forfeited its right to recover attorneys’ fees by failing to give Travelers pre-suit notice. NewcrestImage had filed suit against Travelers to obtain coverage for damage to its hotel property arising out of Winter Storm Uri. In its answer, Travelers asserted that NewcrestImage failed to provide the insurer with pre-suit notice as required under the Texas Insurance Code, and that if NewcrestImage successfully proved it was entitled to coverage, NewcrestImage’s failure to provide pre-suit notice precluded it from recovering attorneys’ fees. Travelers later moved to strike the claim for attorneys’ fees on that basis.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth,
Geoffrey B. Fehling, Hunton Andrews Kurth and
Charlotte Leszinske, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Ms. Leszinske may be contacted at cleszinske@HuntonAK.com
Read the full story...
National Engineering and Public Works Roadshow Highlights Low Battery Seawall Restoration Project in Charleston
April 29, 2024 —
Engineering and Public Works RoadshowCHARLESTON, SC — On Thursday, the nationwide Engineering and Public Works Roadshow stopped at the Low Battery Seawall Restoration Project in Charleston. The event highlighted the role engineers and public works professionals play in infrastructure projects like the local seawall improvements that increase coastal resiliency along the historic urban shoreline.
The event, which took place along the newly constructed battery wall section between King Street and Battery Place along Murray Boulevard, marked the latest stop of the Engineering and Public Works Roadshow – a joint effort by the American Council of Engineering Companies, the American Public Works Association, and the American Society of Civil Engineers to bring public attention to the essential role engineers and public works professionals play in making our modern world possible.
The battery project underscores the importance of innovative engineering solutions in addressing the challenges of climate change and rising sea levels. Thursday's event was also a chance to spotlight the engineering, construction, and public officials involved in the project, whose work often goes unrecognized.
About the Engineering and Public Works Roadshow: The Engineering and Public Works Roadshow is a series of nationwide events highlighting critical infrastructure projects and the skilled professionals who make them possible. It is an opportunity to learn about the importance of infrastructure investment, showcase the work of engineers and public works professionals, and celebrate these projects' positive impact on our communities. Learn more at www.infrastructureroadshow.org.
Don’t Fall in Trap of Buying the Cheapest Insurance Policy as it May be Bad for Your Business Risks and Needs
March 25, 2024 —
David Adelstein - Florida Construction Legal UpdatesDon’t fall in the trap of buying the cheapest insurance policy. It will come and bite you in the butt big time! Consult with an insurance broker that understands construction and, importantly, your specific industry, to provide you coverage within your industry. Otherwise, you’ll be paying for a policy that may (i) not be a good policy, and (ii) may provide you minimal to no value for your industry’s RISKS and NEEDS when factoring in exclusions. When procuring insurance, think of the old adage “penny wise and pound foolish,” and don’t make decisions that fit within this adage!
The recent decision in Nautilus Ins. Co. v. Pinnacle Engineering & Development, Inc., 2024 WL 940527 (S.D. Fla. 2024) serves as an example. Here, a subcontractor was hired by a general contractor to perform underground utility work for a townhome development which consisted of 57 townhome units included in 18 detached structures. The subcontractor’s underground work was defective which caused damage to the property’s water line, sewer system, plumbing lines, pavers, etc. The general contractor was liable to the owner for this defective work. Although the general contractor was an additional insured under the subcontractor’s commercial general liability (CGL) policy, the subcontractor’s CGL carrier denied the duty to defend and initiated an insurance coverage lawsuit. Motions for summary judgment were filed.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Velazquez Framing, LLC v. Cascadia Homes, Inc. (Take 2) – Pre-lien Notice for Labor Unambiguously Not Required
May 13, 2024 —
Travis Colburn - Ahlers Cressman & SleightPre-lien Notice for Labor Unambiguously Not Required.
In January 2024, almost a year after Division 2 of the Washington Court of Appeals decided Velazquez Framing, LLC v. Cascadia Homes, Inc.,1 the Washington Supreme Court, sitting en banc, reversed and remanded the matter for further proceedings.2
The relevant background facts are that Cascadia Homes, Inc. (“Cascadia”), was a general contractor and also owned the property that was the subject matter of the underlying dispute. Cascadia wished to construct a new home on the property. Cascadia hired High End Construction, LLC (“High End”) – a framing subcontractor – to provide framing for the new home. High End, in turn, hired Velazquez Framing, LLC (“Velazquez”). Velazquez did not provide Cascadia – the owner – with notice of its statutory right to claim a lien.
Read the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com