What You Should Know About Liquidated Damages and Liability Caps for Delay and Performance Liquidated Damages
May 06, 2024 —
Chris Cazenave - ConsensusDocsLiquidated damage clauses are omnipresent in today’s construction contracts—often considered in early negotiations to provide a degree of certainty and limit financial liability.
There are two principal types of LDs appearing in construction contracts—(i.) damages for delay when a contractor fails to deliver a project by a certain milestone; and (ii.) performance damages when a contractor fails to meet specific performance requirements. Differentiating between LDs for delay and LDs for performance—especially when both LD types are combined in the same contract—is key to risk awareness and allocation during contract negotiations and throughout performance.
This article briefly outlines what you should know about LDs for delay and LDs for failing to meet certain performance requirements. The article also covers how contractors can allocate and cap risks based on risks each party can either manage, insure, or otherwise limit.
Read the full story...Reprinted courtesy of
Chris Cazenave, Jones Walker LLPMr. Cazenave may be contacted at
ccazenave@joneswalker.com
The Word “Estimate” in a Contract Matters as to a Completion Date
February 12, 2024 —
David Adelstein - Florida Construction Legal UpdatesLanguage in a contract matters. The word “estimates” or “estimated” matters particularly when it comes to a date certain such as a substantial completion or completion date. Remember this.
Here is an example.
In Parque Towers Developers, LLC v. Pilac Management, Ltd., 49 Fla.L.Weekly D190a (Fla. 3d DCA 2024), a trial court held that the developer did not complete the construction of five condominium units by the date in the purchase agreements. The developer appealed because “[t]he agreements contain no date certain for the completion of the units, but rather include a clause that ‘Seller estimates it will substantially complete construction of the Unit, in the manner specified in this Agreement, by December 31, 2017, subject to extensions resulting from ‘Force Majeure (the ‘Outside Date’).’” Parque Towers, supra. Another provision in the purchase agreements stated, “[w]henver this Agreement requires Seller to complete or substantially complete any item of construction, that item will be understood to be complete or substantially complete when so completed or substantially completed in Seller’s opinion. Id.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Congratulations to Las Vegas Team on Their Successful Motion for Summary Judgment!
May 06, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPThis case arose from an alleged trip and fall on an uneven surface in a parking lot outside of BWBO’s client’s restaurant. Plaintiff alleged more than $385,000 in past medical specials (with high potential for future care and treatment) with exposure in excess of $1,000,000.00. The Plaintiff named as Defendants BWBO’s client as well as several entities related to their landlord.
Early in the case, Las Vegas Partner Jeffrey W. Saab and Senior Associate D. Ryan Efros moved for summary judgment based on terms of the restaurant’s lease. They argued that based on the lease, the duty to maintain the surface of the parking lot fell exclusively to the landlord, rather than the restaurant’s client. Plaintiff opposed the motion arguing that the prevailing case law held that any agreement between a tenant and its landlord does not preclude a plaintiff from asserting either or both defendants breached their duties of care. Jeff and Ryan distinguished that case and successfully persuaded the Court that there could be no contractual duty and no common law duty to maintain the parking surface, clearing the way for the court to grant summary judgment.
Read the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
AGC’s 2024 Construction Outlook. Infrastructure is Bright but Office-Geddon is Not
February 12, 2024 —
Garret Murai - California Construction Law BlogThe Associated General Contractors of America has issued its
2024 Construction Outlook. According to its survey of construction contractors throughout the United States, contractors have a mixed outlook for 2024 with firms predicting transitions in the demand for projects, the types of challenges they will face and technologies they plan on embracing. According to the survey, contractors continue to cope with significant labor shortages, the impact of higher interest rates and input costs and a supply chain which, while better than in past few years, is still far from normal.
Of the 17 categories of construction types included in the survey, respondents expected a net positive growth in 14 of those categories, with infrastructure projects leading the net positive readings following the passage of the
Infrastructure Bill in 2021, and commercial retail and office leading the net negative readings as a result of the continuing
office-geddon:
Read the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Is Modular Construction Destined to Fail?
March 11, 2024 —
Aarni Heiskanen - AEC BusinessThe construction sector is a harsh environment for innovation. I’ve been following the story of one Finnish innovative contractor, Lehto Group, over the years with enthusiasm. I was saddened to hear that the group’s three significant subsidiaries joined the ranks of many Finnish contractors who have filed for bankruptcy over the last six months.
Lehto developed industrialized building concepts and had its own production facilities. The company had a promising start but eventually ran into problems. Was the industrial approach a mistake, or were other factors contributing to the firm’s fall?
Three Contributing Factors
Lehto Group’s collapse was not a surprise to its competitors, who had observed warning signs years prior. The company’s order book plummeted in 2024 despite still employing around 500 workers. Rakennuslehti, the leading construction magazine in Finland, asked three experienced industry professionals to give their views on Lehto’s failure. The interviewees spoke anonymously due to the small size of the Finnish market and the sensitive nature of commenting on a competitor’s matters.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
AI and the Optimization of Construction Projects
February 19, 2024 —
Rahul Shah - Construction ExecutiveSeeking answers on how to construct smarter and greener buildings or improve water efficiency in homes and offices, those who create our buildings and construction projects are entering a new era of learning as they turn their attention to the benefits of artificial intelligence.
While human involvement will continue to be paramount, AI has the potential to assist in creating informed decisions, for example by suggesting sustainable, durable materials or cost-effective, but still safe, practices.
The possible applications of AI for the construction industry could be transformative across design, procurement, construction, operation and decommissioning. In fact,
research suggests designers and contractors are already applying AI and machine learning to manage the volumes of data involved in the design of buildings, the planning of construction projects and the day-to-day operations of sites.
Reprinted courtesy of
Rahul Shah, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Natural Hydrogen May Seem New in Town, but It’s Been Here All Along
April 22, 2024 —
Elina Teplinsky & Sheila McCafferty Harvey - Gravel2Gavel Construction & Real Estate Law BlogWhen it comes to renewable energy, hydrogen is hailed as a pivotal resource in the zero-carbon game plan. Hydrogen energy is accessible, produces lower greenhouse gas emissions and can use existing gas infrastructure to power electricity and heat, produce other gases and fuels, and more. Recently, a “new” type of hydrogen—has captured the attention of climate scientists. Natural hydrogen—often referred to as gold hydrogen—stands apart from other, more established types of hydrogen, which require extraction and expensive maneuvering to produce. Natural hydrogen exists underground in its pure form (i.e., it’s not combined with other molecules). Estimates vary, but some researchers suspect that Earth holds as much as
five million megatons of hydrogen beneath our feet. Extracting just 2 percent of that supply, in theory, has the potential to get us to net-zero emissions for 200 years.
From Past Prediction to Accidental Discovery
Viacheslav Zgonnik, CEO of the Denver-based startup Natural Hydrogen Energy,
told the New York Times that Russian chemist Dmitri Mendeleev (also known as the “Father of the Periodic Table”) wrote about the presence of natural hydrogen as long ago as 1888. Somehow, the information was lost along the way, and when pockets of such hydrogen were occasionally found, they were treated as anomalies.
Reprinted courtesy of
Elina Teplinsky, Pillsbury and
Sheila McCafferty Harvey, Pillsbury
Ms. Teplinsky may be contacted at elina.teplinsky@pillsburylaw.com
Ms. Harvey may be contacted at sheila.harvey@pillsburylaw.com
Read the full story...
Partner Jason Taylor and Senior Associate Danielle Kegley Successful in Appeal of Summary Disposition on Priority of Coverage Dispute in the Michigan Court of Appeals
December 11, 2023 —
Jason Taylor & Danielle K. Kegley - Traub LiebermanIn this appeal brought before the Michigan Court of Appeals, the appellate court ruled in favor of Traub Lieberman’s insurance carrier client (the “Carrier” or “Client”), affirming an award of summary disposition in favor of the Carrier in a coverage lawsuit. The coverage lawsuit involved a priority dispute between the Carrier and another insurer over which company’s policy had responsibility to cover the defense of their mutual insured, a heating and cooling contractor (the “Insured”) in an underlying lawsuit alleging carbon monoxide poisoning. The Carrier issued a contractor’s pollution liability policy and the other insurer issued a commercial general liability policy to the Insurer. Both the Carrier and the other insurer filed cross-motions for summary disposition in the trial court on the priority of coverage issue. The trial court granted the Client’s motion, holding that the CGL carrier was the primary insurer based on the language in the policies’ “other insurance” clauses. The trial court rejected the CGL carrier’s argument to apply the “total policy insuring intent” or “closest to the risk” tests—tests which Michigan courts have not adopted. Specifically, the court rejected the CGL carrier’s argument that the Client’s contractor’s pollution liability policy was more specifically tailored to the loss in the underlying lawsuit. The trial court also rejected CGL carrier’s alternative argument that the “other insurance” clauses in the policies were irreconcilable, requiring a pro rata allocation based on the respective limits of the policies.
Reprinted courtesy of
Jason Taylor, Traub Lieberman and
Danielle K. Kegley, Traub Lieberman
Mr. Taylor may be contacted at jtaylor@tlsslaw.com
Ms. Kegley may be contacted at dkegley@tlsslaw.com
Read the full story...